Thermal protection and spalling
The ceiling of the 75m long test zone was protected by the fire protection panels, with a further 25m of the tunnel wall (near the fire) also protected by the boards. Downstream of the board walls, ceramic curtains were employed to protect the rock, mainly to minimise the flow of hot gases above the panel ceiling. Such hot gases could otherwise affect the rock ceiling and the fire protection panels’ steel support structure. Upstream of the board walls, a 9m distance was also protected with ceramic curtains, although not all the way down to the road. This was carried out in order to keep the backlayering gases below the protective ceiling.
It was obvious that this protection was needed during and after the first test, when large blocks of rock fell down onto the road both upstream and downstream of the protection zone. Downstream, the tunnel ceiling was affected almost all the way to the western portal. The upstream spalling resulted from back-layering taking place, in spite of mobile ventilation units (2-3m/s) that were in use. This back-layering was caused by the fact that the air velocity of the fans decreased when the fire intensity grew, increasing the pressure drop over the fire field.
The results can be seen in Figure 4 where the temperatures upstream of the fire during Test 1 are presented. It can be seen that 40m upstream, the temperature is well above 100ºC for a long time period, and as far away as 100m upstream the temperature is close to 100°C.
Radiation levels near the fire
High temperatures give rise to high radiation, which affects the spread of fire to other vehicles. Another important issue regarding radiation is how close fire fighters can advance. Tests performed with fire fighters in protective clothing indicated a limit, approximately 5kW/m² exposure, above which the fire fighters have difficulty working and also feel pain after about five minutes. Measurements during the tests, presented in Figure 5, show that this limit was exceeded in all four tests at a distance of 10m upstream from the set-up. The radiation level 20m upstream of the fire is an important indicator in determining whether the fire brigade can reach the fire with their water jets. Figure 6 shows the measured heat fluxes at this distance. It appears that all heat fluxes remain below the critical level of 5kW/m². The fire brigade were therefore able to approach the fire up to 20m and attack the fire. However, 20m upstream, in the area where the rock was not protected against the fire, at 80°C-100°C, spalling rock was recorded, resulting in large blocks falling in the area where the fire brigade would be expected to work. This would endanger the fire fighters and hamper their ability to work.
Near fire radiation levels and risk of fire spread
The critical level for fire spread is 12.5kW/m². In Test 1 heat fluxes on the floor of 250kW/m2 occur during 15 minutes. In the same test, peak values of 200kW/m² and average values of about 120kW/m² on the walls were observed. At a distance of 5m downstream the heat flux was still 50kW/m². In all tests the critical level for fire spread was exceeded 5m downstream of the fire. The risk of fire spread to a vehicle at that location therefore existed in all tests, but for different lengths of time. In Test 1 the risk existed for 55 minutes. In the other, less severe, tests shorter durations of about 7-10 minutes occurred. More accurate estimations of the risk of fire spread in a HGV fire are planned for the near future, using sophisticated radiation models.